Bringing high level craftsmanship to transmission & distribution networks

CASE STUDIES

66kV AIS Substation Installation - Northwick, Gloucestershire

Introduction

Northwick Estates in Gloucestershire gained permission to construct their own anaerobic digestion system to produce electricity to feed back into the grid.

Wootton & Wootton were contracted to project manage, build & commission a 66KV AIS Substation. Our work comprised of the following:

Scope of Works.

Full time on site project management for the duration of the project

The installation of 1 x Steel Sealing End Structure

The installation of 2 x Steel 66kV Disconnector structures

The installation of 1 x steel 66kV CB structures

The installation of 3 x steel 66kV Post Insulator structures

The installation of 3 x steel 66kV VT structures

The installation of  1 x 66kV CBs

The installation of  2 x 66kV Dis-connector / earth switches

The installation of  1 x set 66kV surge arrestors

The installation of 6 x 66kV Post Insulators

The installation of 3 x 66kV VTs

The Installation of 5 sets 3 phase bus bars

The Installation of 2 sets 3 phase droppers

The Installation of Relay Panel for 66kV Bay

The Installation of AVC Panel for 25MVA 66/11kV Transformer

The Installation of SCADA Panel

The Installation of Interface Wall Box

The Installation of Battery chargers

The installation of 1 x 66KV underground 66KV XLPE Cct

The installation of 6 x 66KV Outdoor Raychem terminations

To Carry out an AC VLF Pressure test

 

Summary.

Despite difficult site conditions the project was delivered on time and on budget

BACK CONTACT US

TESTIMONIALS

CALL US ON  01939 233 009 or 07802 366217